
 

 

 

 


|
The Utility Project Team (UPT) was formed to execute the Lobo Energy,
Inc (LEI) business plan that had been approved by the Board of Regents.
The basic plan is to utilize UNM system revenue bonds to fund the project,
with the savings created by the improvements and new efficiencies to repay
the bonds over a 25-year period. Bonds were issued for approximately $52,700,000
in April 2001. Authorization to issue additional bonds up to $60,000,000
exists if required to complete the project.
Justification for the UPT
The utility generation equipment at Ford Utility Center (Ford) is mostly
from the rebuild completed in 1948. Some equipment was added in the mid-1970s.
However, the normal useful life of this equipment is 15 to 25 years, which
we have far exceeded. The campus is having many problems related to under-capacity
and ineffective supply of primary heating and cooling.
We have also added several aspects to the project in order to increase
the utilities efficiencies, thereby creating the revenue to service the
debt. They are the addition of the ECM work and the Cogen to be installed
at Ford. This creates the opportunity to save energy, and therefore money,
and also expands the generation of electricity to save electrical costs
and reduce UNMs reliance on power cost fluctuations.
Scope of UPT
The UPT scope is broken into three basic subprojects:
Energy Conservation Measures (ECM)
- The Lighting Upgrade project - Lighting upgrades to approximately
90 buildings includes the changing out of more that 150,000 fluorescent
lights from T12 to T8 bulbs, to save 25% on their energy usage. Changing
out all the magnetic ballasts to electronic ballasts will save about
30% on their energy costs.
- The Building Chilled Water Modifications (BCWM) project - Building
Chilled Water Modifications to reverse short-term changes that were
made over the years.
- Design and implementation of the EMCS - Energy
Management and Control Systems Tier I (metering) for a majority of the
90 buildings being served by the utilities division energy supplies,
with direct digital controls (DDC) Tier II (digital control for building
HVAC and other areas) in several of the buildings and interfaces for
communications of these installations back to the utility and maintenance
personnel, in an effort to reduce energy costs.
Chilled Water System Upgrade (CWS)
- The Main Campus Distribution System project - addition of about a
mile each of direct-buried chilled water supply and return lines. This
ties the new chilled water plant to the existing utility systems.
- The Lomas Chilled Water Plant project - a two-story building, having
a nominal 7,300- to 8,000-ton capacity, with future expansion of up
to a 12,000-ton capacity.
- The North Campus Distribution System - upgrades with connections
for the new buildings and balancing of its hydraulics. Lomas Boulevard
crossing, to extend the current connections to the north campus. The
crossing will consist of two 24" pipelines in 30" sleeves
being put through a boring under Lomas Boulevard. This brings all of
the current and future cooling water primarily from the new Lomas Chilled
Water Plant, making the HSSB chiller a backup and the north plant redundant
(the new Childrens Pavilion will displace its location).
Ford Utility Center Renovation (FORD)
- Chiller and Boiler Addition - A new addition on the south side of
the existing structure for the two new chillers and the new replacement
electrical equipment. An addition to house two new boilers appended
to the south side of the existing structure.
- New Ford equipment - A new Cogen facility consisting of two 5.5 MW
GTGs (gas turbine generators) with HRSGs (heat recovery steam generators)
in the existing boiler room. One Cogen will be put in during 2003 and
a second unit scheduled for 2008 or 2009.
- Ford Utilities Equipment Demolition - The five existing boilers demolished
and the boiler room cleared out to make way for the two new Cogen plants.
Demolish the three existing chillers and clear all the equipment out
of that area
- Cogeneration, Control Room, and Tenant Improvements - A new central
control room and miscellaneous shops necessary for running the utility
center constructed in the current chiller room.
Maintaining communication with the campus community
The UPT has established protocols to advise affected
and interested stakeholders of the activities of the projects. In addition,
the team has contributed to several public activities including a display
at the State Fair, numerous presentations to campus and PPD groups, and
tours of the UPT projects.
|