Middle Channel Sand Bar Relocation February 24

Current Opened Gate: #1, 2, and 21.

 

Gates #1, #2, and #21 lowered.  Water level was slightly decreased as 4995.10 ft upstream and 4993.79 ft downstream.

 

 

South intake gate was opened to flush out sediment deposited at the intake trash-rack screen and the fish bypass.  Most sediment was washed away as shown figure below.