Middle Channel Sand Bar Relocation February 24
Current Opened Gate: #1, 2, and 21.
Gates #1, #2, and #21
lowered. Water level was slightly
decreased as 4995.10 ft upstream and 4993.79 ft downstream.

South intake gate was opened
to flush out sediment deposited at the intake trash-rack screen and the fish
bypass. Most sediment was washed away as
shown figure below.