[Task 4] Partially Raised Gates for Low-Flow
Management March 13~14
Task 4, partially raised
gates for low-flow management to develop a curve depicting the results to aid
the City in the event the pool elevation needed to be controlled manually, and
to observe sediment accumulation.
Gates #1 and 2 were fully
opened and gate #17 was 1 ft down on 13-Mar (figure 1). This configuration stayed 24 hours.
On 14-Mar, water depth increased up to 4.2 ft, so the
gates #3 and 4 were opened (figure 2). Purpose
of this configuration is to develop a relationship between the partial gate opening
and water depth change.
However, river inflow discharge is changing
continuously, so the relationship should be considered for gate operation reference
only.
Water depth at each surveying section was taken from
kayak. Figure 2 shows the section XC3 (upstream of the intakes). Comprehensive water depth map of the diversion
dam upstream will be posted soon.
![]()

Figure 1 Figure
2 section XC3
Also, sediment depositions
were deposited along the gate (gates # 9–24 were detected with paddle probing). Especially, at the gates #22-24, huge sand
packs were found as shown in figure 3.
Gates #22-23 were fully opened during the task 3 (6-7, March), and all
gates except gates #23 and 24 were fully opened on last Monday (12-Mar) for cross
section surveying. After only 5 days,
sand bars are relocated, but direction, speed, and volume are not predictable. These huge sand packs can also make gate
operation problems. The sand packs
suppose to be flushing out using gate opening on 15-Mar. Sediment flushing test (certain sand pack volume
flushing speed) will be worth to try.

Figure 3 Figure
4