Central Gate Opening for Removing Sand Bar on Middle
Channel March 27
Current Opened Gate: #13~19.
Gates #13 ~19 were opened to
remove sand bar placed on middle channel.
3.5 ft water depth was measured on PLC screen.
Figure 1 shows the sand bar
(in green circle) placed in middle channel.
The island has been grown up since last week.
![]()
![]()

Figure
1
Sediment deposited in the
north intake bay was discharged with a pump to fish bypass (figure 2). One big fish was found in the south intake bay
(figure 3).
Figure 4 shows one of LiDAR
image taken by Tim and will be used for evaluation of eroded volume (in green
circle).


Figure 2 Figure
3 Figure
4