Gate Trail Operation 31-Jan-07
The upstream water level was
slightly increased for last 5 days of the gate trial operation.
Water levels have been manually
measured by ruler at the upstream deck (5,000 EL.) and downstream sheet file (4,997
EL. (?)). Water level was increased 0.29
ft at the upstream pool in 5 days as shown in the table below. Water head difference between upstream and
downstream was also increased. Main
reason is caused by the gate operation.
Most of the gates have been raised and thus, water level has been
increased at the upstream pool, even though the river discharge has been
deceased at this period as shown in the figure below (Discharge diagram of
|
Date |
Upstream EL. (ft) |
Downstream (ft) |
Head Loss (ft) |
|
28-Jan-07 |
4995.04 |
4994.17 |
0.87 |
|
29-Jan-07 |
4995.17 |
4994.08 |
1.09 |
|
31-Jan-07 |
4995.33 |
4993.17 |
2.16 |
|
Difference |
0.29 |
1.00 |
1.29 |


Due to the lower water level
at the downstream of the dam, sand bars were shown in the west side of the
channel as shown in photo below. If this
gate opening condition (only east side gates opening), sediment will be deposited
to the west side soon for both the upstream and the downstream (upstream sand
bars will not be shown for the high water level).

Sediment deposition along
the fish passage seemed still washed away, although there is no measurement. Water
level at the entry of the fish passage was increased, so inflow rate to the
passage and flow velocity should be increased.
![]()
![]()

Entry of the fish passage Exit
of the fish passage
Recommendations