Middle Channel Sand Bar Relocation February 8~9

Current Opened Gate: #1, #2, #3 and #18.

 

Gates #1, #2, #3 and #18 have remained open since 8-Feb-07 to flush sand bars located in middle channel (figures1 and 2).

The upstream water depth is maintained 3 ft on the PLC screen.  By the way, water depth was maintained 4.31 ft for several hours on 8-Feb to flush sediment along the fish passage (figure 3, taken on 9-Feb). 

Water levels 4995.46 ft upstream and 4993.5 ft downstream were measured on 9-Feb.

 

Gate #1, #2 & #3

 

Gate #18

 
      

Figure 1 [EB1]                                                                       Figure 2 [EB2]                                                                                   Figure 3 [FP4]

 

Most sand bars on the middle of the channel were washed away (figure 4).  

Eroded west bank was recovered this morning (9-Feb) (figures 4 and 5).

 

    

                                    Figure 4 [EB3]                                                                       Figure 5