OVERALL PROJECT HEALTH

Status Item

Current Status

Prior Status

Status Notes

Overall Project Status

GREEN

YELLOW

Change Order #1 submitted to extend the end date until 2-22-08.  New resources have been identified and assigned to the Design Team.

Schedule Status

GREEN

YELLOW

New resources identified and assigned to Design phase

Budget Status

GREEN

GREEN

Within Budget

 

90%+ probability task will meet dates and acceptable quality.

75%+ probability task will meet dates and acceptable quality.  Schedule, resource or scope changes may be required.

<75% probability task will meet dates and acceptable quality.  Schedule, resource or scope changes will be required.

 

Starting Project Budget:  $ 30,000

 

 

 

 

Expense Description

In orig. budget?

Index code

 

Amount Spent

Project Balance

ITIL Overview and foundation Training

$25,000

166020

 

 

ITIL Implementation Road Map Training

$3,000

166020

 

 

Crystal Report Consulting

$2,000

166020

 

 

 

 

 

 

 

Tasks and Activities for Status Period

Finish Date

Ø   Attend Incident Management Design work-session, and work on flow map

On-going

Ø   Prepare for ITSM Steering Committee Meeting

12-6-07

Ø   Distribute Minutes for ITSM Steering Committee Meeting

12-10-07

Ø   Publish Availability Schedule on the Web

11/29/07

Ø   IT Cabinet Presentation – Project overview

12/4/07

Ø   Prototype quick capture screen

12/12/07

Ø   Prototype service request screen

12/14/07

Ø   Meet with Customer Support and Communications for on-call rotation process

12/6/07

Ø   Attend advertising campaign meeting for SLM and ITIL

On-going

Ø   Document Peregrine search process

12-4-07

Ø   Develop VIP list and maintenance

 

Ø   Preview Incident handling by priority with ITSM Steering Committee

12/7/07

Ø   Develop standard OLA template and populate with one existing service 

 

Ø   Update  incident project plan and tasks

On-going

Ø   Notify all managers and supervisors of ITIL training dates

12-4-07

Ø   Attend Essentials of Team Effectiveness Training

12-12-07

Ø   Schedule additional Incident Management Design work-sessions through February

12-13-07

Ø   Static Incident Reports:  http://itsinternal.unm.edu/procedures/incident_management

On-going

 

Tasks and Activities for Next Period

Assignee

Ø   Incident Management Design work-session, continue work on flow map

Design Team

Ø   Meet for advertising campaign for SLM and ITIL

David/Sandy

Ø   Review prototype screens for Quick Capture

Steve Spence

Ø   Review Prototype Screens for Incident and Service Requests

Steve Spence

Ø   Finalize formal on-call rotation

David

Ø   Develop a proposal for Knowledge Engineers for ITS

David/Sandy

Ø   Draft feedback loop between SC and Level 2/3 support

Andrea Rodgers

Ø   Pilot OLA between SC and Level 2/3 support

Andrea Rodgers

Ø   Set  standards for Peregrine data entry

Steve/Andrea/Yvette

Ø   Update Incident Project Plan and tasks

David/Sandy

Ø   Prepare for next ITSM Steering Committee Mtg.

David/Sandy/Louella

 

Project Deliverables

Milestone?

y/n

Responsible Party

Original Plan Date

Actual/Plan date

Ø   Phase 2 – Improved Incident Mgmt. Process map for ITS

Y

Sandy Mayes

11-30-07

Revised to 2-22-08

 

Ø   Phase 2 – Quarterly review of Incident Mgmt. process

N

David McGuire

11-30-07

Revised to 2-22-08

 

Ø   Phase 2 – Training developed and begun

Y

Sandy Mayes

11-30-07

Revised to 2-22-08

 

Ø   Phase 2 – KPIs developed and published

N

Sandy Mayes

11-30-07

Revised to 2-22-08

 

 

Critical Issues

Request Management Assistance? y/n