5.01           ABOVE GROUND STORAGE TANK (AST) PROGRAM

 

The New Mexico Environment Department (NMED) enforces environmental regulations that apply to ASTs at UNM. The Department of Safety, Health and Environmental Affairs (SHEA) coordinates all environmental compliance efforts at UNM, which include those related to ASTs.

 

A.        SCOPE

 

This program is applicable to all UNM entities that manage, operate and maintain ASTs.  It is also applicable to all contractors that work on and near AST systems. The goals of the program are listed in priority as follows:

 

1.         To prevent releases of regulated and hazardous liquids to the environment from

AST systems;

2.                  To comply with applicable laws and regulations governing AST systems; and,

3.                  To detect, report, and correct releases from AST systems should they occur.

 

Program Limitations: Only the environmental compliance aspects of ASTs are covered in this program. Only marginal, if any, mention of related issues involving general safety and fire-prevention are contained herein. These AST-related issues are covered in other UNM SHEA programs including Confined Space Entry, Fire Emergency Action and Evacuation, and Fire Prevention.

 

B.                 DEFINITIONS

 

Applicable Regulations - NFPA (National Fire Protection Association) 30 and 40 CFR 264, 265, and 280.

 

AST - A vessel and associated piping holding regulated or hazardous liquids, for which 10% of the combined volume is not buried and is readily accessible for visual inspection.

 

Regulated or Hazardous Liquids - For the purposes of this program, all petroleum products, hazardous chemicals, and water/chemical solutions which are liquid at 60 °F and 14.7 psia.

 

C.        Operation, Maintenance and Inspection of Existing AST Systems

 

All existing AST systems at UNM are compliant with both environmental regulations and fire code requirements. To remain in compliance, the system components must continue to be both operated & maintained (O&M'd) in accordance with manufacturer recommendations and visually inspected periodically. The follow listing of AST system components describes the regulatory requirements and SHEA’s recommendations:

 

 

 

1.         Tank Leak Detection

 

All existing AST systems at UNM must be visually inspected periodically for leakage by the UNM entity that O&Ms the AST. As long as these systems are operating properly, no tank tightness testing is required. SHEA recommends that the AST system (tanks, piping, dispensers, etc.) be visually inspected at least monthly for leaks and proper operation. A record of these inspections must be kept on-site and made available to SHEA and regulatory agencies upon request.

 

2.         Tanks

 

No O&M or inspection should be required for the tanks themselves if they do not leak.  If sludge build-up or fuel contamination ever becomes an issue, please contact SHEA for assistance with proper disposal and prevention strategies.

 

3.         Spill Protection

 

SHEA recommends that fill port catchment basins be cleaned and the drains tested at least semi-annually to ensure proper operation and to prevent fuel contamination. Water intrusion into the catchment basins may also cause fuel contamination problems. A record of these inspections must be kept on-site and made available to SHEA upon request.

 

4.         Overfill Protection

 

Inspection and testing of overfill protection devices is not currently required. If testing is desired, SHEA does not recommend testing overfill devices in place while filling the tank. Testing can be more safely performed in a water-filled drum or bucket after the device has been removed and cleaned.

 

5.         Piping

 

a.       Pressurized Piping – Annual tightness testing by a contractor with a current NMED Certification is recommended for AST systems with pressurized underground piping. Please refer to the system operations manual or contact the manufacturer on how to perform system checks.

b.      Suction Piping – Tightness testing is not required unless leakage is suspected.

 

6.         Corrosion Protection System 

 

If any AST system is equipped with a corrosion protection system, SHEA recommends that a qualified contractor test the corrosion protection system within 6 months of installation and every 3 years thereafter.

 

 

 

D.        Record Keeping Requirements

 

1.                  SHEA File:

 

a.       The most current NM Fire Marshall (or NMED in future) tank registration certificates;

b.      Copies of the most recent testing results, if any are warranted (see below);

c.       Records of all spills or other releases; and,

d.      Copies of documents sent to EH&S-related regulatory agencies, including any reports, variances, extensions, laboratory analytical results, notices and proposals from AST sites under remediation should be kept indefinitely.

 

2.                  O&M File (on file with the UNM entity that O&Ms the AST):

 

a.       The most recent of any tank and piping tightness testing reports, if any are warranted;

b.      Documentation of  AST system and component installations, upgrades and repairs; including component product information including release detection performance claims, warranties, specifications and other pertinent system information kept for the life of the equipment;

c.       Results of the last 3 corrosion protection systems tests, if such tests are needed;

d.      Records of all spills and releases.

e.       Records of visual inspections for leaks, proper operation, and of fill port catchment basins as described in C1 and C3 above.

 

E.                 Required Reporting

 

SHEA performs all AST-related environmental compliance reporting for UNM. SHEA will need information from the UNM entities which O&M the ASTs including:

 

1.         Registration with the State Fire Marshall’s Office or the NMED.

2.         New system installations and existing system modifications -30 days prior to construction.

3.         Spills, Leaks, and/or Suspected Leaks - >25 gallons may be reported to the NMED.

4.         System closure and leaking tank or buried piping removals require 30-day advance notice to the NMED.

 

F.         New AST Systems and Existing System Upgrades

 

New AST systems and upgraded existing systems must have the same devices described in the O&M section above. SHEA recommends that only contractors with a current NMED UST Installer Certification qualify for work installing AST systems with buried components (e.g., piping). Design and construction of new AST systems and existing system modifications with buried components must have prior approval from SHEA. Additional, new installation requirements and recommendations are described below.

 

 

1.         Corrosion Protection

 

For AST systems with corrodible metal tanks or piping which are not completely protected from contact with soils, SHEA recommends installation of a corrosion protection system. A qualified party must test a corrosion protection system within 6 months of initial installation and every 3 years thereafter.

 

2.         Tank Construction

 

SHEA recommends the following tank constructions in order of preference:

a.       Double-walled tank with monitored interstitial space;  such as a steel or reinforced concrete outer tank and a steel or fiberglass inner tank;

b.      Double-walled steel tanks elevated above grade on saddles; or,

c.       Single wall tank with >3/8” thick steel walls mounted on saddles

 

All ASTs must be protected from vehicles by stout traffic barriers or ballards, where appropriate.

 

3.         Leak Detection

 

All AST systems should have a leak detection system.  SHEA’s preference in leak detection systems is as follows:

a.       Interstitial monitoring with automatic alarm; 

b.      Automatic tank gauging with  0.2 gal/hr loss detection alarm mode capability; or,

c.       Visually inspectable system, including piping, which is visually inspected at least once a month.

 

4.         Piping 

 

No line leak detectors are required. If underground piping is either pressurized, or does not slope back to the AST in a suction pumped system, SHEA recommends that piping tightness tests be performed at least once every 3 years.

 

a.       Tightness Testing Fittings- SHEA recommends that valves be installed on both ends of underground product piping at accessible locations and that a blanked “T” be installed on the high end to facilitate piping tightness testing.

 

b.      Underground Piping Material – SHEA recommends the following piping materials in order of preference:

 

1.         Product compatible plastic piping with solvent-welded joints; or,

2.         Fiberglass piping with solvent-welded joint; or,

3.         Metal piping with cathodic protection.

 

c.       Accessible Aboveground Piping Material – SHEA recommends the following piping materials in order of preference:

 

                        1.         Galvanized steel piping; or,

            2.         Coated/painted black steel piping.

 

5.         Location

 

For AST systems from which there is a possibility for 660 gallons of spillage or leakage of petroleum products or hazardous chemicals to enter a storm sewer or other conveyance leading to a natural water body, UNM will need to develop a Spill Prevention, Countermeasure and Control Plan (SPCCP). SHEA highly recommends locating all new AST systems that are greater than 660 gallon in size sufficiently far away from, or at an elevation below, storm sewer inlets and other conveyances.

 

G.        Closure or Removal of ASTs and Piping

 

All AST system or component closures and removals require SHEA notification.

 

1.                  Qualified Contractors Only – Contractors or maintenance personnel should have a current NMED Installer Certification in order to qualify for work closing ASTs, piping, monitoring systems, especially those with directly buried components or ones with known leakage problems.

 

2.                  Release confirmation soil sampling should be performed for any tank and underground piping removals or closures, and is required for systems with known leak problems.

 

3.                  30-day advanced closure notice to NMED is required to close or remove leaking tanks or  underground piping.

 

H.        Spills, Releases or Suspected Releases

 

1.         Reporting Requirements

 

If an AST system release of any amount is discovered or suspected, inform SHEA immediately. Call 911, if appropriate, for spills or releases of 25 gallons or more. Also, spills or releases of 25 gallons or more may require reporting to the NMED. SHEA will make the reporting determinations and inform the appropriate regulatory authorities. 

 

2.         Corrective Action

 

If corrective action is required for an AST system release, SHEA will coordinate all associated activities. All NMED-required remediation activities will be performed in accordance with an NMED-approved corrective action plan.